HTTP Extension WG

Responsible Parties

Milestones

  1. Present - Mailing list creation, initial discussions and proto-BOF
  2. 1/1/98 - Working group created
    Work begins on FYI and OPTIONS+PEP drafts
  3. 3/98 - Initial Meeting at LA IETF 41 (no BOF)

    First draft of FYI presented
  4. 4/98 - Completion and submission of FYI guidance document
  5. 6/98 - Completion or consensus on OPTIONS+PEP draft
  6. 8/98 - Second Meeting at Chicago
    Submission / Document progress
    Closure of WG as document progress dictates

    Next